Jason A. Crotty is a birder and lawyer living in Portland, Oregon who has been sharing some thought-provoking pieces with 10,000 Birds readers. Jason’s first contribution tackled the importance of the National Wildlife Refuge System, while his second took a deep look at how many birders there really are.

Wind energy is an alternative to burning fossil fuels to generate electricity, but there are consequences to the environment and, in particular, to birds. For example, turbine blades can be lethal to raptors, particularly eagles.

Additionally, some of the best locations for wind farms are sensitive habitat and turbines must first be constructed and then maintained, which requires roads and other infrastructure. Moreover, the power lines needed to transmit electricity from the remote locations where it is generated to the urban locations where it is used can further impact habitat. The result is often litigation, frequently lawsuits initiated by conservation groups.

Steens.Mountain.BLM.01

An occasional look at how these cases actually proceed can be interesting and informative to the conservation-minded birder.

*   *    *

The U.S. Court of Appeals for the Ninth Circuit recently decided a case about whether a wind energy facility could be constructed in remote southeastern Oregon, in Greater Sage-grouse habitat.

Background: The case involved the Echanis Wind Energy Project, a planned 104-megawatt facility consisting of 40-69 turbines that would be located on Steens Mountain in Harney County, Oregon. Although the land on which the facility would be constructed is private, the necessary transmission lines would cross land administered by the Bureau of Land Management (BLM). As a result, the entire project was subjected to the National Environmental Policy Act (NEPA).

NEPA is a federal law that requires agencies to follow certain procedures before commencing a project. One of the most important steps is the environmental impact statement (EIS), which considers a project’s environmental impact, alternatives, and potential mitigation efforts. NEPA is a procedural requirement, meaning the process must be followed, but no particular outcome is mandated. The goal is informed decisionmaking by the agency.

The most important issue in the EIS was the Greater Sage-grouse. The grouse needs sagebrush year-round, but particularly for winter when sagebrush leaves are its only food. But in winter, only some sagebrush habitat is exposed, i.e., not covered by snow, and therefore available to the birds. Such habitat is considered particularly important and it is given the highest priority under Oregon’s sage-grouse management plan. Although it did not actually survey the facility site, BLM extrapolated from two nearby sites and inferred that the grouse was absent in winter.

BLM issued a draft EIS, provided the public with an opportunity to comment, and then issued the final EIS, a comprehensive document that runs 1253 pages. The plan included a number of sage-grouse mitigation measures. (The many BLM documents relating to the project can be found here.)

Wind.Turbine.US.Gov.Work.01

District Court Case: When BLM approved the project, the Oregon Natural Desert Association and the Audubon Society of Portland filed a lawsuit in federal district court contending that the BLM decision was improper.

The conservation groups raised a number of arguments, but the court ruled against them and in favor of BLM in every instance. Agency decisions are typically entitled to deference by courts, meaning an agency decision is presumed correct and the challenging party has a high burden to show that the decision is clearly wrong. In legal parlance, the party must show the decision was “arbitrary, capricious, an abuse of discretion.” Deference is particularly appropriate when an agency is making scientific or technical judgments within its area of expertise, as in the case of land management by BLM.

The judge determined that BLM collected sufficient data and made reasonable decisions based on that data, finding the BLM’s actions were not arbitrary and capricious. The conservation groups appealed to the Ninth Circuit.

Steens.Mountain.BLM.02

Ninth Circuit Appeal: On appeal, the conservation groups argued that BLM failed to assess “baseline conditions” at the site by doing an actual count rather than an extrapolation from nearby sites. Although a baseline is not itself a requirement of NEPA, the court stated that it was a “practical requirement.” Without a reasonable baseline, the court reasoned, there was no way for BLM to assess the project’s impacts and, therefore, no way to assess alternatives or mitigate any adverse impacts.

Thus, the court held that BLM had a duty to assess the actual site. Additionally, the court stated that several sage-grouse were found at one of the nearby locations during a winter survey. Given that, the inference should have been that grouse were at the site during the winter. Moreover, BLM’s consultants suggested that the site was good winter habitat for the grouse and stated that an actual survey should have been conducted.

Although BLM is generally entitled to deference, the court held that “deference does not excuse the BLM from ensuring the accuracy and scientific integrity of the analysis, a NEPA requirement.”

Nonetheless, errors are not fatal if they are “harmless.” But the court found that the inadequate winter baseline analysis “materially impeded informed decision making and public participation.” Moreover, if there are wintering grouse on the site, the site would be critical habitat under the Oregon sage-grouse management plan. Such habitat is deemed irreplaceable and cannot be destroyed because mitigation is inadequate.

Thus, the court reversed BLM’s lower court victory. The consequence is that the project will either be delayed or abandoned, as it appears that BLM will have to conduct a thorough winter grouse analysis at the site if the project is to move forward. The developer will also have to assess its options in light of the decision by the Ninth Circuit.

*   *   *

Judicial decisions such as this do not turn on abstract weighing of the relative importance of birds and renewable energy. Rather, they turn on glamourless issues of administrative law, namely whether an agency followed the proper procedures and made reasonable decisions after considering all of the information it obtained.

There will continue to be conflicts between renewable energy facilities and birds and their habitats, as each is important. Although these lawsuits can be opaque, they do have an impact.

Greater.Sage.Grouse.USFWS.01

Photos: Greater Sage-grouse: Jeannie Stafford/USFWS; Steens Mountain Cooperative Management and Protection Area: BLM.

Written by Jason Crotty
Jason Crotty is a birder, lawyer, and occasional writer currently living in Portland, Oregon with his wife and daughter. A Bay Area native, he started birding while working at a large law firm in San Francisco, but birds less frequently now that there's a kid around, so he writes instead. Jason started at 10,000 Birds with a few guest posts and signed on as a beat writer in March 2017. He is particularly interested in the intersection of law and birding (especially the Endangered Species Act), other bird-related federal litigation, and federal public lands. Jason's writing has also appeared in BirdWatching, Birding, and Birder's Guide, both online and in print.